The International Canal Monuments List
Individual structures
A Locks
Fundamental to the ability of any navigation to rise or fall
was the use of lock-gates to hold one stretch of water at a higher
level than an adjoining section.
Single (or "flash") lock-gates were in use by the 1st century
BC (Chien-Lu Dam and canals near Nanyang) but may have been used
earlier (in the valley of the Euphrates, or the port of Sidon) for
irrigation and sluicing purposes.
In Europe, the lock was developed initially to overcome two
specific problems: a desire to allow boats to enter a drainage and
navigable water system which was protected by dykes, and the need
to increase the depth of water available for the navigation of
rivers. For the former use they were originally of the single
lifting gate portcullis type, while staunches or weirs with
removable wooden boards sufficed for the latter, boats sailing up
or down the river on the "flash" of water released when the boards
were removed. The earliest single-gate locks were built in the
Low Countries at Nieuwpoort and in Italy on the river Mincio at
Governolo in the late 12th century, though there had probably been
river staunches in Flanders earlier in the century.9 At the end
of the 14th century the opening of the Stecknitz Canal in Germany
(1398) was the first summit canal in Europe, a progression made
possible by the use of single locks.
The main problem with "flash" locks and single gates was that
they used large volumes of water unless the levels on either side
of the gate was equal. Two lock-gates placed close together made
a huge saving in water and time in lock-use. This, the "pound" or
"chamber" lock, originated in China by the 10th century AD and may
have been in use in the Netherlands by the 14th century. A basin
between the gates was capable of holding one or more boats. The
chamber lock radically reduced water usage. The first recorded
example (1373) in Europe was at Vreeswijk (Netherlands), where the
canal from Utrecht entered the river Lek.10 The use of the lock
in more upland canal schemes was pioneered in 15th-century Italy
with the building of a lock in Milan in 1420.
For very large steep sites the lower gate of one lock might
form the upper gate of another. A Chinese text of 1072 mentions a
staircase pair of locks.11 In Europe they were first used in
France, when the Canal du Briare (France) opened in 1642, 39 years
after the first plans had been drawn up (A History of
Technology, 3, 460-3). In staircase locks, the upper
gate of the lowest lock also forms the lower gate of the second
lock, and so on up the flight. This method of construction reduced
costs but caused hold-ups when boats working in opposite
directions needed to use the locks. More importantly, from a
canal engineering viewpoint, they were inefficient users of water,
and canals on which they were built often had water-supply
problems.
The two greatest of these early lock staircases are the eight
lock rises at Fonserannes (Béziers) on the Canal du Midi
(France) and at Banavie (Neptune's Staircase) on the Caledonian
Canal (Scotland, UK). The Rideau Canal in Canada also made
considerable use of staircase locks, with a great eight-lock rise
at Ottawa. Technology transfer from the Caledonian Canal led to
the seven-lock flight at Berg on the Göta Canal (Sweden),
where Thomas Telford was consultant, using his Caledonian Canal
drawings as the basis for the Göta's Locks.12 In his turn
Telford had learnt from the engineering of the Canal du Midi, for
in his library at the Institution of Civil Engineers in London are
copies of the two older books (1778 and 1804) on the Canal du Midi
with annotations in Telford's hand on them.13
A major improvement in the design of locks was the mitre
gate. Because of the stresses involved, a single wooden gate
restricted the width of lock which could be constructed. The mitre
gate, where two gates meet at an angle on the centre line of the
lock, increases the width of lock it is possible to build. The
mitre gate was probably introduced in Italy by Bertola da Novate,
though the earliest drawings are by Leonardo da Vinci and date
from the late 15th century.
The early locks built in China and Italy were of stone, but
elsewhere turf-sided locks were often used, where the section of
lock between the gates consisted of sloping turf-covered sides.
Vertical wooden guides were used to stop boats from sticking to
these sloping sides. Such locks used larger amounts of water than
conventional stone locks owing to leakage. They can still be
found on the River Kennet Navigation in England and on the
Grossefehn-Kanal near Emden (Germany). Wood was also used for the
construction of locks, and a wooden lock survives from the old
Maryinsk Canal (1810) in Vitegra (Russia).
A feature developed on French canals in the 17th century was
the ground paddle, or sluice built into the stonework of the lock,
which controlled the flow of water from the upper to the lower
level. Previously locks had been emptied and filled by sluices in
the gate. This restricted the depth of to which a lock could be
built, as the water flowing through the gate paddle into a deep
lock would flood the boat using the lock. By placing the sluices
and their channels into the structure of the lock, water could be
fed into the bottom of the lock without the possibility of
flooding boats.
When the Canal du Midi was built, the side walls of the locks
were built curved, making the centre of the lock wider than the
gates. It was thought that this would counteract the forces
tending to push out the side walls of the locks when the lock was
empty. This disregarded the fact that when the lock was full the
water provided a similar, but reversed, force, and consequently
locks are better built with straight sides. However, several
canals were built with curved lock sides, including the Canal de
Castille in Spain (1790s) and the original Saimaa Canal in Finland
(1845-56).
Water supply was the canal engineer's main problem, and there
are hints in the documentation that the Grand Canal in China used
side ponds to save water. Side ponds were built such that their
level was half-way between the upper and lower levels of the lock.
When emptying, the first half of the locking water could then be
fed into the side pond, and this water could be used subsequently
for filling the first half of the lock. Many European 18th- and
19th-century locks, such as the flight at Devizes on the Kennet
and Avon Canal, were built with side ponds between locks.
In central and eastern Europe, double-width locks were
sometimes constructed which allowed two boats to lock through
together. Single-width gates were provided and these were offset,
to the right at one end of the lock and to the left at the other.
The first boat entered the lock and then moved over to allow a
second boat to enter. The first use of such locks may have been
on the Finow-Kanal (Germany) when it was rebuilt in the 1830s.
They can also be found on other canals in Germany and on the Labe
and Vltava in the Czech Republic.
Towards the end of the 19th century there was a growth of
interest in canal engineering in Europe as more canals were
planned and built. To reduce costs and to decrease the time taken
to pass through them, locks were designed and built deeper than
previously. This would have caused excessive stresses with mitre
gates, so the shaft lock was successfully developed. In these,
the lower end of the lock was enclosed by a wall, boats entering
and leaving through a hole in the lower part of the wall. Both
mitre gates and vertical lifting gates were used to seal this.
Shaft locks, because of their depth, used large quantities of
water. To reduce this usage chambers were built into the side
walls of the locks which acted as side ponds. Up to five or six
chambers could be used, one above the other on each side of the
lock.
The earliest known (but unsuccessful) shaft lock was built on
the line of the uncompleted trans-Sweden canal at Trollhättan
in 1754. This was on the Karls Grav and had a fall of no less
than 16m. Unfortunately the shaft-lock proved unusable in
flood-time owing to insufficient height in the entrance tunnel,
and in 1768 it was replaced by a staircase pair of locks.14
Improvements in lock design have continued throughout this
century, with different types of gate design appearing. These
have included gates which lift and rotate, increasing headroom
under the raised gate, gates which slide to one side, gates which
lower either sliding vertically or are hinged at the bottom, and
sector and segment gates which are curved and thus distribute
stresses more evenly. Gates are also now used for emptying and
filling locks, doing away with the necessity for sluices and
paddle gear.
S I T E S
a Single-gate locks
An important non-canal site in the evolution of the
single-gate lock is the port of Sidon (2nd century BC or earlier);
there are still extant Phoenician harbour works there, where
rock-cut grooves (one still remaining) indicate the former
existence of four sluice-gates, probably for flushing the harbour.
These could well go back to the 8th-12th centuries BC.15
| i | Nile to Red Sea Canal Lock (Egypt), rebuilding
by Pharaoh Ptolemy II (Philadelphus), c 285 BC. |
| Grading: 1. ***; 2. ***; 4. ***.
Total: 9 | | | Diodorus Siculus wrote of this 97km canal that the
Pharaoh: "... in the most suitable spot constructed an
ingenious kind of lock. This he opened, whenever he wished
to pass through, and quickly closed again, a contrivance
which usage proved to be highly successful."16 |
| ii | Magic Canal (China) (see "Contour canals"). |
| Grading: 1. **; 2. ***; 4. *. Total: 6 |
| iii | Duckerschleuse, Stecknitz Canal (Germany) Single-
gate flash-type lock. |
| Grading: 1. *; 2. **; 3. **; 4. *. Total: 6
| | | Eight kilometres north of Lauenburg, a town with a long
tradition of inland water transport, on the Elbe, 30km east
of Hamburg (Germany), the lock is close to the village of
Witeeze. Alongside the lock is the lock-keeper's house. As
boats only used the lock infrequently, the lock-keeper was
also a farmer. The house is now used as a cafe and guest-
house. The lock is currently under restoration. To gain
access to the site, it is necessary to cross the Elbe-Trave
Canal, which replaced the Stecknitz Canal in 1900, at Witeeze
Lock. This, and the other locks on the canal, was built to
the Hotropp design. Water is used to operate the gates by
counterbalances and the sluices are activated by air, and
also compressed by water flowing from the upper level to the
lower.
Other associated sites include the Palm-Schleuse in
Lauenburg, a circular chamber lock capable of accepting
several of the small Stecknitz canal barges at one time.
This lock was built in 1724 on the site of an earlier single-
gate lock. It is named after Herr Palm, who was the local
miller (the mill is next to the lock) and lock-keeper (see
"Summit-level canals" for other details of this waterway). |
b Double-gate locks
| i | Grand Canal (China), 984 AD. |
| Grading: 1. ***; 2. ***; 4. ***. Total: 9 |
| |
The first recorded double-gate or pound lock in the
world was built at the northern end of the Shan-yang Yun-Tao
section between the Yangtze and Huai-yin in AD 984 by Chhiao
Wei-Yo, Assistant Commissioner of Transport for Huainan.17 |
| ii | The Conca di Viarenna, Via Arena, Milan (Italy), c
1400. |
| Grading: 1. ***; 2. ***; 4.*. Total: 7 |
| | In 1179-1209 a water-supply and irrigation canal was
built over the 50 km from an intake on the river Ticino
(running from Lake Maggiore) to the Po, southwards to
Abbiategrasso and east to the south side of Milan. In 1269
this was enlarged and made navigable as the Naviglio Grande.
In 1386 work began on the new cathedral that was being built
with marble from quarries near Lake Maggiore. Boats were
raised the 2m to the level of the city moat by stopping the
flow of the Naviglio Grande at the most convenient times and
raising its level to that of the moat with stop planks. The
boats passed into the moat and on to a short canal to the
cathedral site. When the boats had passed, stop planks were
used to cut off the moat and reopen the Naviglio Grande. The
procedure was reversed to allow boats to return. A staunch
(single-lock gate) was then provided at the entrance to the
linking canal at Viarenna, and later a second at the junction
between the moat and the Naviglio Grande, to replace the stop
planks. The engineers Filippo da Modena and Fioravante da
Bologna created Italy's first pound lock (one of the first in
Europe) by bringing the two lock gates nearer together to
reduce water consumption. A second pound lock was built on
the enlarged old moat by 1445 (now renamed the Naviglio
Interno). The various sections of the Naviglio Interno have
now either been culverted or filled in. |
c Lock staircases
| i | Rogny Staircase, Canal de Briare (France), 1605-10.
[Figure 1] |
| Grading: 1. **; 2. **; 3. **; 4. **. Total: 8 |
| | The first staircase flight of locks in Europe is
situated 130km south of Paris, 15km NE of Briare. From the
point of view of technological innovation, this is a more
important flight of locks than those on the Canal du Midi
(see below). The canal was supplied with water from two
lakes which fed its summit level. The flight of seven
"staircase" locks at Rogny was at the northern end of this;
they have straight sides and are fitted with ground paddles.
When the latter were introduced to the United Kingdom (on the Newry Canal in
Northern Ireland) the locks were described as "after the
French pattern." These original locks were bypassed at the
end of the 19th century and they remain as substantial
structures. |
Figure 1 The large early 17th century lock staircase
at Rogny, Canal de Briare (France)
| ii | Fonserannes (Béziers) Staircase, Canal du Midi
(France), 1665-81. |
| Grading: 1. **; 2. **; 3. **; 4. ***. Total: 9 |
| | Original eight-rise staircase on the Canal du Midi (see
section on "Technologically significant canals"), built
1665-81. The upper six locks are still in use and the lower
two, below a later diversion of the canal, are used
occasionally. Most traffic now uses the new "water-slope,"
completed in 1983. |
| iii | "Neptune's Staircase," Caledonian Canal (Scotland,
UK), 1803-11. |
| Grading: 1. *; 2. *; 3. ***; 4. **. Total: 7 |
| |
This 60-mile canal was designed to carry sailing ships,
up to 170ft by 40ft, through the Great Glen of Scotland.
Thomas Telford was principal, with William Jessop as
consulting engineer. Telford had assembled a specialist
construction team and the scale of the work set a precedent
with the large use of construction railways and three steam
engines for pumping. With the large lakes on the summit
level of the canal there was no shortage of water. The locks
were therefore placed in groups to save expense: at Bonavie
was built the "Neptune's Staircase" of eight locks, at Fort
Augustus five, at Muirtown another four, and double locks at
Corpach and Laggan. The locks were designed for a navigable
depth of 20ft, but the canal itself did not reach a depth of
17ft until 1847. The locks remain in substantially their
original condition and are all still in active use on the
Caledonian Canal (see Paget-Tomlinson 1978, 106). |
d Earth-sided locks
These represent an early and primitive type of lock used on
river navigations that have sometimes survived in use into the
modern period.
| i | Garston Lock, Burghfield, Kennet Navigation, England
(UK), c 1854. |
| Grading: Grading: 3. ***. Total: 3 |
| |
This is a conserved turf-sided lock, originally built
in 1715-23 as part of the Kennet Navigation from Reading to
Newbury. The survival of parts of a timber substructure
indicate a rebuilding in c 1767 to a length of 37m and
a width of 5.8m (with a lift of 2.5m) so that it could
accommodate "Newbury" barges. It was absorbed as part of the
arterial Kennet and Avon Canal and rebuilt as a smaller
(27.6m long and 4.6-5.2m wide) turf-sided lock, revetted with
slate, in c 1854. The lock was brought back into
operation after conservation in 1993-94.18 |
e Wooden-sided locks
Another primitive type of lock that has remained in use
intermittently.
| i | Wooden-sided lock at Vitegra (Russia). |
| Grading: 3. ***. Total: 3 |
| |
350km ENE of St Petersburg, on the southern shore of
Lake Onega. This is the last remaining lock of the 39 built
(size given as 74m by 10.3m) on the Maryinsk Canal, dating
from 1810. The canal, which linked Lake Onega with
Tcherepovetz, was repeatedly reconstructed and was awarded
the Grand Gold Medal at the 1903 Paris International
Exhibition as an outstanding example of Russian engineering.
In the 1960s the canal was rebuilt to much larger standard
and reopened in 1964. |
f Mitre-gated lock chambers
Single tall and heavy gates both restricted the width
of a lock chamber and were heavy to move. The introduction
of double mitre-gates, which were kept closed by the pressure
against them, became universal.
| i | Spaarndam (The Netherlands), early mitre-gated chamber
lock, 1572. |
| Grading: 2. *; 3. *. Total: 2 |
| |
This is the site, 15km west of Amsterdam, of a chamber
lock which possibly used mitre gates and was built in 1572.
The lock allowed passage between the river Spaarne and the
Haarlemmer (which was eventually drained by the Cruquis
pumping engine). It is possibly on the site of an earlier
lock dating from the mid-14th century. Also in the village
are flood control sluices, a later stone-built lock, and a
large modern lock. It is possibly worth considering because
of the location's long history of hydraulic engineering.
There were earlier structures here, and today there are two
more recent locks close to the site. |
g Shaft locks
| i | Saint Denis Lock, central Paris (France), 1892. |
| Grading: 2. **; 3. **. Total: 4 |
| |
This was the first successful shaft lock. The Saint
Denis Canal was rebuilt c 1892 to accommodate the
deeper boats which were being built for the recently dredged
Seine. The number of locks was reduced, and in one place a
single lock, with a fall of 10m, replaced four older ones.
This was the first shaft lock to be built, the lower end of
the lock being traversed by a masonry bridge, which was also
used to contain the water in the lock when the single gate
fitted against it.19 |
| ii | Horin Lock, near Melnik (Czech Republic), 1905. |
| Grading: 2. **; 3. *. Total: 3 |
| |
This is an early shaft lock with offset gates, later to
become a common feature. This lock, located close to the
confluence of the Labe and Vltava rivers, is a shaft lock
dating from 1905. It has twin lower gates which form a
straight seal against the bridge section across the lower
mouth of the lock. The lock gates are offset to allow two
boats to use the lock simultaneously. |
| iii | Anderten Lock, Hannover (Germany). |
| Grading: 2. *; 3. ***. Total: 4 |
| |
This shaft lock and associated complex, 5km east of
Hannover, on the Mitteland-Kanal, built c 1930, raises
the canal to its summit level. There are two locks, 225m by
12m, side-by-side. Five chambers, one above the other, are
built into each lock side to conserve water. A water pumping
station to feed the summit level is also built on the site.
This lock, with its large size and water economy measures,
represents the direction in which waterway engineering has
proceeded up to the present.20 |
B Inclined planes
The idea for transporting boats over dry land must have grown out
of the necessity in ancient times of having primitive rough
portages around rapids on rivers, or to connect two arms of the
sea across an isthmus. The Greeks called this a diolkos,
and one of the earliest and largest, with a paved way, rails, and
terminal slipways, was at Corinth (see below).
Differences of height on a canal line could also be overcome
by pulling boats up ramps between varying levels of water, which
overcame many of the water-supply problems generated by heavy
lockage.
It was realized in China at an early date that if the ramp of
a spillway was made to slope at a reasonably gentle gradient it
would be possible to drag canal boats up and over it to the higher
level. In this manner the double slipway was developed. This
consisted of a pair of inclined stonework aprons over which boats
were hauled, in China generally with the use of capstans, from a
waterway at one level to a waterway at another. In 1696 Lecomte
described the use of one as follows:
At the end of the Canal they have built a double
Glasis, or sloping Bank of Freestone, which uniting at the
point, extends itself on both sides down to the Surface of
the Water. When the barque is in the lower Channel they
hoist it up by the help of several Capstans to the plane of
the first Glacis, so far, till being raised to the Point, it
falls back again by its own Weight along the second Glacis,
into the Water of the upper Channel, where it skuds away
during a pretty while, like an Arrow out of a Bow; and they
make it descend after the same manner proportionably. I
cannot imagine how these Barques, being commonly very long
and heavy laden, escape being split in the middle, when they
are poised in the Air on this Acute angle ...
Passages of the slipway only took 2.5-3 minutes and European
observers considered them much preferable to conventional pound
locks, since it was also possible to construct them at a quarter
of the expense.21
There was probably an indigenous development of the double
slipway in Europe. This, the overtoom, was in use in the
Netherlands by 1148, when there were two examples in use on the
Nieuwe Rhijn Canal near Utrecht; there was probably another at
Spaarndam in 1220 and elsewhere in Europe at Ypres in 1298.
The next stage in development was for rope-hauled short
inclines to convey boats in wheeled cradles as had been used on
the Corinth diolkos. In Italy a particularly well known
one was that erected in 1437 at Lizzafusina or Zafosina on the
river Brenta at Fusina near Venice (see below).22
It was gradually realized that larger inclined planes could
be used in very hilly country to overcome large changes in level,
initially with the use of very small boats. In such situations
the alternative would have been the use of great flights of locks,
expensive to build, slow to use, and requiring large amounts of
water. The other, less common alternative, was a boat lift (see
below).
A Sardinian-born engineer, Daviso de Arcort, was the first to
design such long inclines on small "tub-boat" canals in hill
country. He probably knew of existing short Italian inclines from
first-hand knowledge of from books such as Leone Battista
Alberti's De re aedificatoria (1485) or Cornelius Meijer's
L'Arte de restituire a Roma la tralasciata navigatione
(1685). In 1767 he began the construction of three inclined
planes on a canal from Drumglass collieries, County Tyrone
(Ireland), towards the river Blackwater. The eminent British
engineers John Smeaton and his assistant William Jessop suggested
that these inclines should be made double and counterbalanced.
Davis Ducart (as de Arcort was known in Ireland) then substituted
cradles on rails rather than the rollers on wooden ramps he had
previously built. Even with these crucial innovations these
inclines were abandoned largely unused.
The first successful modern inclined planes were those used
in Shropshire (UK) from 1788 onwards. The international evolution
of the canal inclined plane is a good example of international and
intercontinental technology transfer. In 1795 a small inclined
plane based on the Ketley type was built at Hadley, Massachusetts
(USA), and in 1796 the American engineer Robert Fulton published
his Improvements in Canal Navigation, partly based on his
study of the Coalbrookdale planes. François de Recicourt,
a French military and civil engineer, had a translation of
Fulton's book produced in 1799. Fulton visited France from 1797
to 1801 and the French engineers Bossu and Solages built one
incline and a lift at Le Creusot between 1801 and 1806.23
The underground incline at Worsley (Manchester), on the
Bridgewater Canal in Britain, was built at the end of the 19th
century and linked the main canal tunnel level with one of the
other three levels which served the coal mine. It was
particularly important for the way it was reported on, and because
it caught the international imagination.
In 1824 the Pennsylvania Society sent the engineer William
Strickland to Great Britain to study railway construction, and it
was subsequently that the astonishing Allegheny Portage Tramroad
was built as part of a composite railway and canal link, with no
less than ten powered inclined planes. Later in the 19th century
engineers from abroad studied the Morris Canal inclined planes in
the USA and built canals with inclined planes in Poland and Japan.
S I T E S
| i | Corinth diolkos (Greece), early 6th century BC. |
| Grading: 1. ***; 2. **; 3. **; 4. *. Total: 8 |
| |
This was not strictly a canal line, but it did involve
the movement of ships inland, pioneering the use of boat or
ship cradles, and so it is included in this list. The
diolkos was a stone-paved ship-railway with slipways
at either end that traversed the 4 miles across the Isthmus
of Corinth and remained in use until the 9th century AD. A
roadway of stone blocks had very broad and shallow grooves of
5ft 6in gauge with an inner edge 4ft 11in apart. There was a
passing place on a curve with double tracks. Ships were
carried on wheeled cradles running in these stone-way
grooves. Remains of part of the track have been excavated.
Stone-track railways of later date are not uncommon; one of
the more complete ran the 10 miles from granite quarries at
Haytor on Dartmoor down to the navigable river Teign (Devon,
England).24 |
| ii | Double-slipways on the Chinese Canals. |
| Grading: 1. ***; 2. **; 4. **. Total: 8 |
| |
Some were still in operation in 1934 (see section on
the Grand Canal in "Technologically Significant Canals").
The specific site location of well preserved remains need to
be established. |
| iii | Short incline at Lizzafusina, or Zafosina, on the
River Brenta dam, near Venice (Italy). |
| Grading: 1. **; 2. ***. Total: 5 |
| |
This dam stopped the river waters from silting-up the
salt water of the Venetian lagoon. Boats were transported
over the dam on a short incline, positioned on two strong
cradles on wheels, drawn up by a rope passing over an axle
which was worked by a horse gin. The surviving illustrations
show a double-incline without any evident means of
counterbalancing. The wheels of the cradle ran in grooves,
as at Corinth, rather than the later use of upstanding
rails.25 |
| iv | The three inclines built by Daviso de Arcort near
Coalisland, County Tyrone, Northern Ireland (UK),
1767-77. |
| Grading: Grading: 1. **; 2. ***; 3. *. Total: 6 |
| |
The first was on the Drumglass colliery canal 862m from
Coalisland basin with a rise of 16.7m; the second was 772m
further on at Drumreagh House, with a rise of 20m. The third
was just west of Farlough Lake, with a rise of 21m. The
inclines were originally to be single water-wheel powered
ramps, but there proved to be insufficient water and so
counterbalanced railed inclines were substituted with horse
gins to help the 2-tonne boats over the sills. Little
traffic passed the inclines and they were abandoned in 1787.
There may have been insufficient water for the working of
the upper canal or the inclines may have been too steep for
effective counterbalanced working. Substantial remains of
these first long inclines, the first also fitted with
upstanding rails, and the first to be worked by
counterbalanced working, can still be seen. They were also
important for sowing the idea of canal inclined planes in
Britain and Ireland as the Industrial Revolution was
starting.26 |
| v | Hay Inclined Plane, Ironbridge Gorge Museum, Shropshire
(UK). [Figure 2] |
| Grading: 1. *; 2. ***; 3. ***; 4. *. Total: 8 |
| |
The first successful modern inclined-plane was that
built by the Shropshire ironmaster William Reynolds in 1788
at Ketley near the modern town of Telford in 1788, with a
vertical lift of 22.25m. It was counterbalanced, loaded
boats descending on cradles running on rails. The first
steam-powered inclines were then constructed by the same
builder on the adjacent Shrewsbury Canal, which opened in
1791-92, the greatest having a rise of 63m.27 This, the Hay
inclined plane leading down the side of the Severn Gorge, has
been re-railed and forms part of the Ironbridge Gorge Museum
(a World Heritage site). Detailed drawings were made by
French engineers and disseminated widely. |
Figure 2 The 1790s Hay inclined plane at the
Ironbridge Gorge World Heritage site, England (UK)
| vi | Underground incline, Worsley, Bridgewater Canal, Manchester
(UK). |
| Grading: 1. **; 2. *; 3. *; 4. **. Total: 6 |
| |
Deep coal-mining tunnels were built from the end of the
Bridgewater Canal from its inception in 1759. By 1795 this
level of underground waterways and one 32m above it extended
for 24km. They may not have been the first underground
mining canals in Britain but they attracted many visitors
from home and abroad, who helped to spread the idea of canal
mines widely and who also reported on this underground
inclined plane.28 The idea for the inclined plane was put
forward by the originating mining engineer, John Gilbert, and
construction took place between September 1795 and October
1797. It was sited on a 1 in 4 incline following a sloping
bed of gritstone 4km from the surface entrance of the mining
canals and was 138m long with the upper part consisting of a
double railway 5.8m wide. At peak capacity it was capable of
handling 30 boats each way in an 8-hour shift, a total weight
of around 915 tonnes. The incline was abandoned in 1822 with
the exhaustion of the upper shallow seams, but substantial
remains survive underground.29 |
| vii | Allegheny Portage Railroad, Pennsylvania (USA),
1831-34. |
| Grading: 1. ***; 2. *; 3. ***; 4. *. Total: 8 |
| |
The 394 miles of the Pennsylvania Main Line was a
unique composite canal and railway line linking Philadelphia
and Pittsburgh, opened between 1826 and 1834. Built over
mountainous terrain, and only made possible by the extensive
use of steam-powered inclines, it was even more astonishing
an innovation than the pioneering Erie Canal itself. Both
passengers and goods could travel the whole distance without
transshipment by the use of sectional boats that could be
divided into three or four units. The 132km eastern section
was operated as a horse and locomotive railway, but the 60km
central section consisted of the Allegheny Portage Railroad
with five steam-assisted counterbalance inclines reaching up
and over Allegheny Mountain. Sylvester Welch built the
railway over a 712m summit in three years. The Pennsylvania
canals were a crucial step in establishing the industrial
might of the most powerful nation on earth.30 |
| viii | Elblag Canal (Poland), an outstanding example
of a canal still in operation with multiple 19th-century
inclined planes. |
| Grading: 1. *; 3. ***; 4. *. Total: 5 |
| |
Between 1844-60 in what was then East Prussia, the
Oberland or Elbing (now Elblag) Canal ran from the Frisches
Haff (near Elblag) and the Geerich lake to Osterode. The
canal originally had four counterbalanced inclined planes
with waterwheel-powered assistance. In 1881 a fifth inclined
plane with water-turbine power replaced five of the seven
locks. 60-tonne barges have now been replaced by the regular
use of passenger tour-boats. The original four inclines of
20-24.5m in rise were designed after study of America's
Morris Canal.31 |
| ix | Biwako Canal Inclines, Kyoto (Japan), 1885-90. |
| Grading: 1. *; 2. ***; 3. *. Total: 5 |
| |
The Biwako Canal is an outstanding example of
intercontinental technology transfer. The designer, Sakuro
Tanabe, toured the USA (including the inclines of the Morris
Canal) to study current practice in canal engineering and
hydro-electric practice. It has one of the world's first
hydro-electric power stations and in many ways is the climax
to the building of 19th-century small canals.32 The canal
connected Lake Biwa (Biwako) to Kyoto via the counterbalanced
Keage Incline. This has double-track inclines of 2.5m gauge.
The incline descended 36m towards the City of Kyoto in a
length of 555m on a gradient of 6.48%.33 The twin
steel-built boat cradles and the incline are preserved.
There was also a second incline. |
C Boat lifts
Some mid-18th century canals such as the Bridgewater in England
used vertical haulage of loaded containers to overcome differences
in level. The idea of lifting an actual boat from one canal level
to another seems to have evolved separately in both England and
Germany at the end of the 18th century.
The first recorded boat lift was constructed in 1788-89 on
the short Churprinz Canal at Halsbrücke in Saxony (Germany).
This was for small 2.5-tonne boats and involved the use of a
five-fold manual tackle. The lift continued in use until 1868
(see "Sites" below).34
The more sophisticated experimental lifts built in the last
decade of the 19th century in Britain were generally unsuccessful.
These included deep shaft locks with caissons and boat cradles
supported on pillars supported by floats immersed in under-lift
tanks.35
Subsequent lifts have been largely successful. In the early
1830s the Grand Western Canal in the south-west of England was
opened with no less than seven counterbalanced twin-chamber lifts
and operated successfully until 1867 (see "Sites" below).36
Hydraulically operated lifts were the big success stories of
the late 19th and early 20th centuries. Edwin Clark (1814-94) was
the engineer behind their development, and it was his designs that
have led to the widespread practical use of the lift. In 1846
Robert Stephenson appointed him to be superintending engineer to
the Britannia and Conwy Tubular Bridges, the wrought-iron tubes of
which were raised using hydraulic presses. In 1857 he became
engineer to the Thames Graving Dock Limited, for which he designed
a graving dock in which the ships to be repaired were lifted from
the water by hydraulic presses. In 1866 he lectured on this, by
which time the lift had been working for about seven years and had
raised 1055 ships with an average tonnage of 686 tonnes.
A connection was made between the Weaver River Navigation and
the Trent and Mersey (at Anderton, Cheshire, UK) using a 15.35m
lift to Edwin Clark's design with two counterbalanced troughs.
The hydraulic cylinders extended 21.35m below each tank. The lift
was set in operation by removing some centimetres of water from
the lower caisson. The speed of operation was controlled by
transferring the hydraulic fluid through a 0.127m pipe from below
one caisson to the other. The descending caisson became immersed
in the canal water and for the last 1.22m had to be assisted by a
steam-powered hydraulic accumulator. Boats of 102 tonnes could be
raised in the 22.88m by 4.73m tanks. In 1904 the lift was
converted to electrical operation because of chemical corrosion of
the rams.37
Edwin Clark, his brother Latimer, and John Standfield went on
to design a series of lifts on the European mainland in
conjunction with the well known French engineering works, SA des
anciens établissements Cail. Les Fontinettes lift was
built to replace five locks in northern France in 1880-88 and
could raise large 300-tonne barges in caissons 38.6m by 5m (see
"Sites" below).38
During this important example of technology transfer to the
European continent several developments were made on this larger
lift that were to be important in later examples. Edwin Clark
decided that the lift pits should be kept dry which did away with
the necessity for the troughs to be moved for the final short
distance by a hydraulic accumulator. A structural innovation was
the introduction of masonry towers which supported the troughs at
their centre-points and also supported the operator's cabin.
The hydraulic presses for operating the rams were made of
cast-iron at Anderton and were designed to be of such at Les
Fontinettes. However, on 26 April 1882, the side of one of the
Anderton presses blew out during operation and so the Les
Fontinettes presses were made of steel with a thin lining of
copper. Water-turbines also provided the extra power needed to
operate the lift and blow the seals on the gates.39
The last lifts to be built under the auspices of Messrs
Clark, Standfield & Clark were the unequalled concentration of
four added to the Canal du Centre; the first was built
simultaneously with the Les Fontinettes Lift and opened on 4 June
1888. The building of the last three was delayed and they were
opened in August 1917.40
Three other hydraulically operated lift schemes illustrate
intercontinental technology transfer. The British engineer James
Brunlees proposed a ship railway across the Central American
isthmus in 1872. This was to take vessels of at least 1220 tonnes
on six rails holding 60 four-wheel bogies. Propulsion would be by
steam-powered rack-locomotives and ships would be got out of the
water and returned to it by hydraulic lifts. This scheme was
never built. H G C Ketchum, who had worked with Brunlees, then
proposed a 27.4km ship-railway across the Chignecto peninsula that
would save a 800km sea journey around Nova Scotia for shipping
travelling from the eastern seaboard of the USA to the Gulf of St
Lawrence. Ships of up to 2032 tonnes would be positioned over a
gridiron and carrying cradle in a lifting dock at either end of
the railway. The gridiron would then be raised by 20 hydraulic
rams and presses and the ship on its cradle hauled on to the
railway. The Chigneto Marine Transport Railway Company was formed
in England by James Brunlees and Edwin Clark in 1883 and over half
the work of construction was completed between 1888 and July 1891,
when the company ran out of money. Remains of the formation
survive.41
There followed the construction of two successful lifts on
the Trent Canal in Ontario (Canada). These were constructed at
Peterborough in 1896-1902 and in 1900-07 at Kirkfield. These
followed on from earlier designs but are significant for being an
example of intercontinental technology transfer. The
still-operating Peterborough Lift, with a rise of 19.5m, was the
highest hydraulic lift built.42
The next lifts moved away from the technology of having twin
caissons counterbalanced by hydraulic pressure. Both of the next
types - counterweighted and those using floats - were foreshadowed
by early experiments: Woodhouse in the former case and Rowland and
Pickering or Bossu and Solages in the latter case.
The Henrichenburg Lift in Germany was built between 1894 and
1899 to give access to Dortmund from the Dortmund-Ems Canal. This
raised large 950-tonne craft through vertical rises of 14.5m.
Five floats in a row beneath the caisson rose or fell in their
respective pits as the water-level was changed. An experimental
English lift had first used the system in 1796.43
An international competition for boat-lift design took place
in 1902. A jury of international experts, including Sir Vernon
Harcourt, considered over 200 designs for boat lifts to be used on
the proposed Danube-Oder-Elbe Canal. Although the canal was not
built (it is still being promoted), the designs became the
inspiration for many of the boat lifts that were built
subsequently.44
In Britain chemicals in the canal water caused problems with
the hydraulic operation of the pioneering Anderton Lift, and in
1903-08 its system of operation was altered. The steam-power that
had operated the accumulator was replaced by electricity. Over
the next few years the hydraulic rams were taken out and each
caisson was then operated separately by electric power assisted by
counterweights.
S I T E S
| i | Churprinz Canal Lift, Halsbrücke, Saxony (Germany),
built 1788-89. [Figure 3]
|
| Grading: 1. ***; 2. **; 3. **. Total: 7 |
| |
The Churprinz Canal ran for 5.3km on the bank of the
Freiberger Mulde river in order to carry ore to the
Halsbrücke smelting works from the
Churprinz-Friedrich-August mine adit. The whole operation
was labour-intensive, with 2.5-tonne boats being towed by two
men, a third man on the boat steering with a pole. The river
was crossed on the level with the stone-built lifthouse
entered through an arch on one bank. This was a rectangular
chamber 5.5m wide and 17m long up which boats were lifted by
a five-fold tackle into the upper level of the canal. Bad
weather and high water in the river could disrupt the working
of the lift but it continued in use until 1868. The
substantial remains of the lift are still extant.45 |
| ii | Grand Western Canal Lifts, Devon (UK), designed by
James Green and built in 1832-35. |
| Grading: 1. **; 2. *; 3. **. Total: 6 |
| |
The first successful twin-chamber counter-balanced
canal lifts; in use until 1867. The biggest of the lifts
rose 13m and there are substantial remains at Nynehead lift
(7.32m). Two counterbalanced iron tanks were suspended by
pulleys within a masonry framework.46
A lift important to the evolution of canal lifts
(but not on a canal) was the ship lift at the Thames Graving
Docks, Royal Victoria Dock, Woolwich, London, designed by
Edwin Clark and built in c 1859. The lift was sited
in a channel connecting the Royal Victoria Dock at Woolwich
and the Pontoon Dock that lay on its south side and was the
first of all the lifts using hydraulic power to lift vessels. |
| iii | Anderton Canal Lift, Weaver Navigation/Trent and
Mersey Canal, Cheshire (UK), designed by Edwin Clark and
built in 1872-75. |
| Grading: 1. ***; 2. ***; 3. **. Total: 8 |
| |
This is important for being the first hydraulic canal
lift and the first of a series of large late 19th and early
20th century lifts based upon it. Boats are carried through
a lift of 15.35m in one of two tanks or caissons: 22.9m x
4.73m x 1.53m, encased within an iron framework. Each
caisson, weighing 244 tonnes with its water, was originally
supported in the centre by a 0.915m diameter iron ram
extending downwards into a cast-iron hydraulic press with a
0.127m diameter pipe originally connecting it to the press
beneath the second caisson. 0.1525m of water removed from
the lower caisson were enough to start the lower caisson
falling, its descent being controlled by the rate of flow of the water in the interconnecting
0.127m pipe. Since 1908 each caisson has been operated
independently by electric power and two rows of
counterbalance weights. The lift has been conserved as an
ancient monument and is being restored to use.47 |
Figure 3 The 18th century Churprinz canal lift at
Halsbrücke (Germany)
| iv | Les Fontinettes Lift, Neufosse Canal linking the Pas de
Calais ports to the Canal de St Quentin (France),
1883-88. |
| Grading: 2. **; 3. ***. Total: 5 |
| |
The first large continental European lift, it bypassed
no less than five old locks on a flight dating from 1760.
The rise was rather less than Anderton but the capacity was
much greater: 38.5m long, 305-tonne Freycinet standard barges
drawing 1.8m of water. The design was that largely adopted
on future lifts with central towers steadying great steel
tanks that were cantilevered out from each side of the
central rising column. The old locks were kept in case of
breakdown but the lift was so successful that it carried
11,161 boats in 1905. A single large lock replaced the
structure in daily use in 1967 and it remains as an
industrial monument.48 |
| v | Canal du Centre Lifts (Belgium), 1888-1917. |
| Grading: 1. **; 2.*; 3. ***. Total: 6 |
| |
The difference in levels between the two ends of the
canal was 89.45m and there were two distinct sections of the
waterway, one of 13 km having five locks with a total rise of
23.26m and the other of 8km with a rise of 66.19m. To
overcome part of the latter rise the 15.4m high La
Louvière lift was opened in 1888, with the other three
lifts of 16.93m rise opening in 1917. The first lift was
designed by M P Nolet, an engineer at the
Société Cockerill, Seraing, employed by Clark,
Standfield & Clark. The framework of this lift was lattice
girders rather than the masonry of Les Fontinettes. This
unique concentration of lifts carried boats of 404 tonnes.
All four of the Canal du Centre lifts have been replaced in
use by the 73.15m Strepy Lift but are to be preserved.49
The lifts form part of an integrated industrial
landscape, with the early continental European coal-mining at
Bois-du-Luc, recommended as being of world significance by
the TICCIH Board. |
| vi | Peterborough and Kirkfield Canal Lifts,
Trent-Severn Waterway, Ontario (Canada), 1896-1902 &
1900-07. |
| Grading: 1.*; 3. **. Total: 4 |
| |
These followed on from earlier designs but are
significant for being an example of intercontinental
technology transfer. The still operating Peterborough Lift,
with a rise of 19.5m, was the highest hydraulic lift built.
It was also one of the world's largest concrete structures at
the time of its completion: more than 19,890m2 of concrete
were poured. The commercial success of this link between the
Great Lakes was impaired by there only being money available
to build two small-scale inclined planes at two further
changes of level. The second lift, at Kirkfield, illustrates
the progression to a lighter steel structure. A large lock
and bigger incline have now allowed more intensive use of the
lifts, which are conserved with the canal by Parks Canada.50 |
| vii | Henrichenburg Lift (Germany), 1899. |
| Grading: 1.*; 3. ***. Total: 4 |
| |
Situated on the Dortmund-Ems Canal, the site dates from
1899, when the first boatlift was built. The tank of this
lift is supported on five flotation cylinders fitted
underneath. It soon proved inadequate to cope with the
volume of traffic and a shaft lock with side chambers was
built close by in 1914. By the 1960s, boats had increased in
size, so a new lift was built, this time with just two
flotation cylinders. This in turn has been supplemented in
1989 by a new shaft lock, capable of accommodating a 2000-
tonne push-tow unit. This complex of structures illustrates
the rapid development in scale of 19th and 20th century
waterways and could be considered for any designation as a
group.51 |
D Earthworks
The civil engineering of the artificial waterways had to develop
in order to allow the line of water channel to be conveyed over
undulating countryside.
Because of the problems in moving the large volumes of earth
required and the difficulty in understanding soil stability, large
embankments did not feature on the earliest canals. It also
accounts to some extent for the use by the Romans of aqueducts,
rather than earthworks, for their water supply systems.
By the late 18th century, engineers began to overcome these
problems. One of the greatest of the early embankments was at
Burnley, on the Leeds and Liverpool Canal (UK), where the canal is
carried 1km over the valleys of the rivers Brun and Calder at a
height of over 12m. The section of the Leeds and Liverpool Canal
between Burnley and Wigan, built between 1796 and 1816, features
eight large embankments and shows the confidence then being
discovered by canal engineers.
The British engineer Thomas Telford was involved in three
notable early uses of large-scale earthworks. These are, first,
the approach embankments to the Pontcysyllte Aqueduct on the
Ellesmere Canal, Wales (UK), dating from 1795-1805 (see
"Aqueducts" and "Technologically significant canals") and,
secondly, the great embankment at Shelmore and the nearby Tyrley
(Woodseaves) Cutting, Shropshire (UK). The third of his works
noted here is the Smethwick Cutting, a 3660m cutting up to 20m
deep on Telford's low-level line for the Birmingham Canal, one of
the greatest excavations to that date in Britain.52
The construction of the great ship canals - Manchester, Kiel,
and Panama - saw the mechanization of earth movement and the
ability to construct the vast cuttings on those canals. The
largest embankment to be built on a conventional canal was the
Raguser Dam, Brandenburg (Germany) on the Havel-Oder Canal.
Opened in 1914, it carries the canal some 28m above the valley of
the river Raguser. The embankment has a cross-section of 2800m2
and contains around 1 million m3 of earth.53
E Reservoirs
A most important aspect of canal engineering is the adequate
supply of water. The height of a canal's summit level is dictated
by the method of supplying water. Early canals, such as the 1398
Stecknitz Canal (Germany), had low summit levels, which were
supplied with water directly from lakes, rivers, and streams. The
Canal de Briare (France) of 1642 was also supplied from existing
water supplies, but the water supply to the Canal du Midi (1681)
came from dams and water feeders built specifically for that
purpose (see "Dams").
Large European ecclesiastical and monastic estates of the
Middle Ages had sufficient resources and need for a moderate
development of waterway transport, and the first recorded
navigation dam survives from this period.
S I T E S
| i | Alresford Dam and 200-acre (80ha) reservoir, Itchen River
Navigation, (UK). |
| Grading: 1. ***; 2. **; 3. **. Total: 7 |
| |
The earthen dam is overgrown but still holds 24.3ha of
water. This was the first known navigation dam in the
world.54
Seven hundred years ago the area around Winchester, the
early medieval capital of England, was prosperous because of
its wool and cloth industries. In 1189 Godfrey de Lucy,
Bishop of Winchester, decided to improve the commercial
potential of the area by making the river Itchen navigable
along its entire length between Alresford and Southampton
Water. This work required the construction of a series of
flash locks whose subsequent operation depended on a supply
of water in excess of the river's natural flow. Bishop de
Lucy therefore constructed a reservoir just to the north of
Alresford which stores the water of two small streams (see
"Dams"). |
| ii | Reservoir on the Grand Canal (China), c 1411. |
| Grading: 1. **; 2. **; 3. ***. Total: 7 |
| |
A reservoir with a 1 mile long dam on the Kuang River,
north of Ningyang. This is the second known recorded
navigation dam in the world, built around 1411.55 (see
"Dams" and "Technologically significant canals"). |
| iii | Canal du Midi reservoirs and feeder system
(France). [Figure 4] |
| Grading: 1. **; 2. ***; 3. ***; 4. **. Total: 10 |
| |
The Canal du Midi was a summit-level canal with a heavy
lockage requiring a large quantity of water. To the north of
the canal's summit, suitable sources of water were found in
the rivers of the Montagne Noire. Pierre-Paul Riquet planned
a 42km long feeder system in 1661. The only drawback was
that more water than was needed was available in the winter,
and less in the summer. He therefore took the logical step
of building a reservoir to store the surplus winter run-off
for use during the following summer.
The dam of St Ferréol was built across the river
Laudot about 2 miles south-east of Revel. Later, a second
dam was required, the stone Lampy Dam, built by the canal
engineer Garripuy in 1777-81 (see "Dams"). |
Figure 4 Low-level outlet tunnel in the base of the
large earthwork reservoir dam of Saint Ferréol,
Canal du Midi (France), 1667-71
F Water pumps
Water usage on canals with heavy lockage could be enormous and
might easily outstrip the water supply available from gravity
feeders. The use of pumps goes back to at least the end of the
11th century AD, when there are Chinese references dated 1098 and
1120 to batteries of hand-pumps built to supply water to summit
levels and probable references to pumps mounted on pontoons that
were used to pump water back at pound locks.56 The Archimedean
screw was extensively used on canals, not so much for water supply
as for ensuring dry conditions when construction or maintenance
work was being undertaken.
On the first canals of the Industrial Revolution at the end
of the 18th and the beginning of the 19th century power pumps
began to become fairly common: they were powered by water-wheels
and steam engines. Two of the more significant early examples are
listed below. Two more steam-engine houses have significant
remains at Smethwick on the Birmingham Canal mainline (see
"Technologically significant canals").
During the later part of the 19th century, manual and animal-
powered pumps used for maintenance purposes were replaced by
steam-driven reciprocating and centrifugal ones. Generally,
Archimedean screws were used for water supply where there was only
a low head to overcome, such as on river navigations. At
Locquinol on the river Sambre (northern France), an electrically
powered screw pump is still in operation. It was formerly driven
by a steam-powered beam engine which is preserved on site.
On the Mitteland Canal, in Germany, there are impressive late
water-pumping systems at Minden (c 1914), and at Anderton,
Hannover (c 1930).57
S I T E S
| i | Crofton pumping station, Kennet and Avon Canal (UK),
begun in 1800. |
| Grading: 1. *; 2. *; 3. ***. Total: 5 |
| |
This pumping station was intended to supply the summit
level of the Kennet and Avon barge canal that runs across
southern England. The brick-built engine house with its
separate iron-bound chimney stands above the canal near the
village of Great Bedwyn and not far from Hungerford. It
houses the only Boulton & Watt engine still doing the work
for which it was originally installed. Built in 1812, it is
the oldest working steam engine in the world.
There was also an earlier Boulton & Watt engine which
began work here in 1809. Both were low-pressure engines,
fitted with Watt's parallel-motion linkage and his patent
separate condenser. The 1812 engine was converted to
high-pressure working in 1844, and a Sims engine was
installed to replace that of 1809. The latter was rebuilt in
1905 when new Lancashire boilers were added. The Sims engine
worked until 1952 and the 1812 one until 1958, when the top
6m had to be removed from the chimney and the steam-engine
pumping was replaced by electric pumps. Restoration of the
steam-pumps began in 1968 and both steam engines have been
regularly operated since 1971, the 1812 engine raising 1
tonne of water at a stroke. |
| ii | Claverton water-powered pumping station, Kennet and Avon
Canal (UK), 1813. |
| Grading: 1. *; 3. ***. Total: 4 |
| |
This installation lifts water 16m from the river Avon
to the Kennet and Avon Canal. A tall Bath-stone building
houses the original beam-worked bucket pumps with the smaller
wheelhouse alongside. There was originally a breast
waterwheel 7.6m (25ft) wide and 5.58m (18ft 4in) dia In 1858
this was replaced by two 4.73m (15ft 6in) dia waterwheels on
a single shaft, each 3.36m (11ft) wide. A small diesel pump
replaced them in 1952, but restoration began in 1969 and the
waterwheel pumps are now run on a regular basis.59
There was a third pumping station on the Kennet and
Avon Canal and the remains of this are now within the World
Heritage site of the Georgian City of Bath. The ornamental
stone chimney of this former pumping station is situated
halfway down the six-lock (formerly seven) flight leading to
the river Avon. The old steam-engine house is at the bottom
of the flight.
The World Heritage site at Bath also includes two iron
arch bridges (7m and 9.15m in span) over the canal cast at
Ironbridge in 1800 and sited in the 18th-century Sydney
Gardens and adjacent to the elegant classical canal offices
which straddle the canal on a bridge. |
G Aqueducts
A canal used a natural resource, water, as the medium of its
transport way. Deep natural obstacles needed to be bridged by
large structures, including a waterproofing medium. Until the
19th century the technology of building masonry walls and arches
was better understood than the science of soil mechanics, which
was required to design stable earthworks. Before the advent of
steam-powered machinery aqueducts were more practical to build
than large earthworks. Such structures bridging natural
watercourses also ensured the separation of the artificial
water-economy of the canal from the natural land drainage and
considerably eased the water management of the artificial
navigation.
Non-navigable aqueduct bridges, often of considerable size
and length, were common in antiquity. One of the first recorded
was built by King Sennacherib of Assyria (c 705-681 BC) on
the 50-mile long water-supply canal to his capital at Nineveh from
springs at Bavian. This Jerwan aqueduct was 305m long and 11.9m
wide and an inscription was excavated in the present century that
read "I caused a canal to be dug to the meadows of Nineveh. I
spanned a bridge of white stone blocks. These waters I caused to
pass over it."60
The Romans built huge lengths of high arches carrying
channels waterproofed with hydraulic mortar. Some 1600 million
litres of water daily poured into Rome through eleven great
aqueducts. Across low-lying land, particularly outside towns, an
aqueduct had to be raised high enough to give a sufficient "head"
to the supply, and the use of arches both removed a potential
barrier to communication and lessened the amount of stone required
for construction. The water-channels above the arches varied from
0.46m to 1.2m wide and from 0.6m to 2.4m high.
The Aqua Marcia (144 BC) actually forms part of a three-deck
aqueduct at the Porta San Lorenzo gate into Rome; the arches of
the gate also carry the Aqua Tepula (127 BC) and the Aqua Julia
(33 BC) aqueducts. Probably the finest Roman aqueduct is the 72km
of the Aqua Claudia, built by the Emperors Caligula and Claudius
to bring water from Subiaco to Rome. Part of its length is on
solid masonry and for 15.3km it is borne on lofty arches, some
over 30m high, great lengths of which remain in the Campagna. It
is joined 3 miles from Rome by the Anio Novus (AD 38), 99km in
length.
Technology transfer over the large extent of the Roman Empire
was especially noteworthy. The Pont du Gard (c AD 14) at
Nîmes (France), which is on the World Heritage List, was
part of a 40km long aqueduct to bring water from the neighbourhood
of Uzès. The aqueduct bridge itself has a triple arcade
carried 47km above the river Gard and is 270m long, of largely
unmortared masonry. The double arcade of the aqueduct at Segovia
(Spain), dating from c AD 10 and also on the World Heritage
List, is another of the more remarkable water-supply bridges
spread throughout the Roman Empire.61
Such water-supply, irrigation, water-power, and dual-purpose
aqueducts continued to be built into the modern period and have
had a significant influence on those built primarily for
navigation.
It is arguable that the birthplace of highly engineered
canals in the modern period was in 15th-century Italy. A
navigable canal aqueduct was built on the Martesana Canal from the
river Adda to Milan between 1462 and 1470. The Canal du Midi was
the largest civil-engineering enterprise of its time and by 1661 a
large 9.15m (30ft) span aqueduct had been built on its line at
Répudre. The Duke of Bridgewater, inspired by a visit to
this canal, planned the first major canal of the world's first
Industrial Revolution. This included a three-arched aqueduct
carrying the canal 11.6m above the navigable river Irwell, the
central arch being 19.2m (38ft) in span.62
Waterproofing varied, with the earlier continental European
examples often using hydraulic mortar whereas most British
examples used vast amounts of puddled clay - an unstable
waterlogged mass.
The scale and monumental character of the masonry aqueduct
developed considerably in the first new national integrated
transport network that served England's first Industrial
Revolution and produced such superb masonry structures as the
Lune, Dundas, and Marple Aqueducts.
Iron as a constructional material for girder bridges was used
by the ancient Chinese by AD 1000, and in the modern period first
for large arches of wrought iron, as at Kirklees, Yorkshire (UK),
and then cast iron over the river Severn at Ironbridge, Shropshire
(UK) in 1779 (part of the World Heritage site). It was only a
matter of time before the material was applied in aqueducts.
The world centre of the iron trade at the beginning of the
19th century was Merthyr Tydfil, Wales (UK), which successively
had the two largest ironworks of the 19th century. It was here in
1793 that a two-deck water-power aqueduct was constructed with the
lower deck and trough made of iron: the Pont y Cafnau. A sketch
of this appeared in the sketchbook of the Shropshire ironmaster
William Reynolds in 1794, when he was working on the first
large-scale navigable aqueduct made out of iron at Longdon-on-Tern
in Shropshire in conjunction with Thomas Telford. This project
led on to Jessop and Telford's Pontcysyllte Aqueduct with its 307m
long and 38.4m high iron trough, the loftiest navigable canal
aqueduct ever built. On the way were several aqueducts that
combined cast-iron and hydraulic lime in their waterproofing, such
as Chirk and the Edinburgh and Union Canal aqueducts.
The USA had aqueducts that served its developing New World
economy, cheaply built in timber with a limited life-span but
which enabled the local economy to develop and thrive via
accessible cheap transport. Some of these were of great length,
and the immense weight of the water carried ensured that these
were not simple wooden troughs but had strong lateral
reinforcement. One of the Delaware and Hudson Canal aqueducts
designed by John Roebling and completed in 1847 survived after
conversion to a road bridge. It is the earliest wire-cable
suspension "bridge" in the world to retain its principal original
elements.63
In the 20th century reinforced concrete became the standard
material used for large-scale canal aqueducts. Notable are the
reinforced-concrete aqueduct at Minden (Germany) of 1914, which
crosses the valley of the Weser (375m long and Europe's longest
canal aqueduct)64 and the remains of the unfinished concrete
aqueduct (1939) which was to cross the Elbe at Magdeburg, and
which it is currently proposed to complete. This may mean that
the existing remains will be removed.
S I T E S
| i | River Molgora Aqueduct, Martesana Canal, near Milan
(Italy). |
| Grading: 1. ***; 2. ***; 3. ***; 4. *. Total: 10 |
| |
In 1462-70 Bertola da Novate, engineer to the Duke of
Milan, built his second large navigable canal (29km long)
eastwards from Milan to near the river Adda at Groppello,
then north for 8km to its intake at Trezzo. It had a small
three-arched aqueduct over the river Molgora; the river
Lambro was also culverted under this canal, which also had
two staunch or flash locks. There are remains of this
waterway.65 |
| ii | Répudre Aqueduct, Canal du Midi (France), 1665-81. |
| Grading: 1. *; 2. ***; 3. ***; 4. **. Total: 9 |
| |
The whole line and the scale and sophistication of all
its engineering works were an inspiration to succeeding canal
engineers in the Industrial Revolution. Other aqueducts over
the Orbiel and Cesse rivers were designed by the French
military engineer Sébastien Vauban and built by
Antoine Niquet on the Canal du Midi in 1686.66 |
| iii | Pontcysyllte Aqueduct, Ellesmere Canal, Wales (UK),
1795-1805. [Figure 5] |
| Grading: 1. ***; 2. ***; 3. ***; 4. *. Total: 10 |
| |
One of the heroic monuments that symbolizes the world's
first Industrial Revolution and its transformation of
technology. Thomas Telford, the Ellesmere Canal "general
surveyor and agent," was working under William Jessop, the
most prolific engineer of the British canal mania. The
relative roles of these two engineers in the design is not
totally clear.67 The construction of this landmark, the
highest navigable canal aqueduct built, led to the formation
and consolidation of a team important to the subsequent
development of civil engineering on such large projects as
the Caledonian Canal.
The decision to build such a high deck, and in the new
civil-engineering medium of cast-iron, was a bold one. The
canal surface is carried 38m over the river Dee on an
iron-arched deck, 313m long, comprised of nineteen spans of
13.6m (44ft 6in). The 3.6m (11.8ft) wide trough is carried
on successive spans of four arched ribs spanning between
slender masonry piers, which are partly hollow and taper to
3.96m (13ft) by 2.29m (71ft) at their summit. The southern
approach embankment was one of the largest earthworks built
up to this time.68
Other aqueducts linked to the genesis of this structure
might also be associated in any designation. Pont y Cafnau
was a cast-iron aqueduct whose construction was authorized in
1793 in order to carry both a water-supply channel and a horse-worked railway
into what was the largest ironworks in the world by the early
19th century at Cyfarthfa, Merthyr Tydfil, Wales (UK). A
sketch of this done in 1794 survives in William Reynolds's
sketchbook. Also in this collection of papers is a sketch
made by Telford of a design for a high iron aqueduct made in
1794. Reynolds was the ironmaster who was experimenting,
together with Thomas Telford, in 1795 on the first iron canal
aqueduct to be designed. This Longdon-upon-Tern aqueduct is
a protected monument 57m long, with four spans of 14.5m (47ft
8in), and a trough 2.7m (9ft) wide and 0.9m (3ft) deep. One
month before it was completed in 1796 a much smaller
single-span iron canal aqueduct was built by the engineer
Benjamin Outram (William Jessop's business partner) on the
Derby Canal (demolished 1971).69
On the Ellesmere Canal, near Pontcysyllte, the earlier
Chirk Aqueduct had a cast-iron base to the water-channel, and
Telford went on to advise a further group of three very large
aqueducts with cast-iron channels on the Glasgow and
Edinburgh Union Canal in Scotland (see the section on
"Technologically significant canals").
|
Figure 5 The huge cast-iron aqueduct of Pontcysyllte,
Wales, 1795-1805
| iv | Delaware River Aqueduct, Lackawaxen, Pike County,
Pennsylvania (USA). |
| Grading: 1. **; 2. *; 3. **; 4. *. Total: 7 |
| |
The ambitious Pennsylvania Main Line (see "Inclined
planes") of 1826-34 entered Pittsburgh at its western end by
passing over a 348m long wooden-trough aqueduct over the
Allegheny River. The pioneering engineer John Roebling
replaced it in 1845 with a new one of seven 49.4m (162ft)
spans reinforced by wire suspension cables.70 In 1847 two
rivers formerly crossed by the Delaware and Hudson Canal on
the level were given two of the four new aqueducts commis-
sioned from Roebling by the canal company.71 The Delaware
River aqueduct survived after conversion to a private road
bridge and was carefully restored in the 1980s and conserved
as a National Historic Site.
This is the earliest wire-cable suspension bridge in
the world to retain its principal original elements.72 The
bridge runs from Pennsylvania into Minisink Ford, Sullivan
County, New York. There are four spans of 43m (141ft 5in)
from the centre of one 2.9m (9ft 6in) wide suspension tower
to the next. The stone piers and abutments carried the 2.6m
(8ft 6in) deep trough 9.5m above the level of the river.
The wooden floor of the trough was held by wrought-iron
hangers from the suspension cables that were largely hidden
in the side-bracing for the wooden canal trough, with the two
towing paths being almost at the level of the top of the low
suspension pylons.73 Barges of 132 tonnes used the canal
from 1852. |
Next - Individual Structures - part II
References and Notes
9 C Singer, A History of Technology, 3, 442.
10 T Telford, "Canals," The Edinburgh Encyclopedia,
15, 209-315: Edinburgh, 1830.
11 C Hadfield, op.cit., 23.
12 C Hadfield, Waterways Sights to See, 41: Newton Abbot,
1976.
13 L T C Rolt, From Sea to Sea: The Canal du Midi,
5: London, 1973.
14 C Hadfield, op.cit.,1986, 55.
15 J Needham, Science and Civilisation in China,
4.III, 350-51.
16 C Hadfield, op.cit., 1986, 17; Hahn et al.,
op.cit., 3.
17 J Needham, op.cit., 350-51. Chhiao Wei-Yo was
Assistant Commissioner of Transport for Huainan in AD 983 at
the beginning of the Sung Dynasty. He was concerned with the
barge traffic problem at the northern end of the Shan-yang
Yun-Tao section of the Pien or Grand Canal between the
Yangtze and Huai-yin. Exasperated with the thefts of
tax-grain made possible by the high casualty rate of ships
crossing the double slipways, the Sung Shih says that in AD
984: "Chhiao Wei-Yo therefore first ordered the construction
of two gates (tou men) at the third dam along the West
River (near Huai-yin). The distance between the two gates
was rather more than 50 paces [250ft], and the whole space
was covered over with a great roof like a shed. The gates
were "hanging" or portcullis gates (hsuan men); [when
they were closed] the water accumulated like a tide until the
required level was reached, and then when the time came it
was allowed to flow out."
18 P A Harding, An Archaeological Survey and Watching
Brief at Garston Lock, Kennet and Avon Canal, Industrial
Archaeology Review, 17.2, Spring 1995, 159-70.
19 Annales des Ponts et Chaussées, July 1893,
44; Transactions of the Institution of Civil
Engineers, 115.2, 1892-93, 429-31.
20 Personal communication, Michael Clarke.
21 J Needham, op.cit., 363-64.
22 Ibid., 364-65, and D Tew, Canal Inclines and
Lifts, 3: Gloucester, 1984.
23 C Hadfield, op.cit., 1986, 71.
24 J Needham, op.cit., 364.
25 D Tew, op.cit., 3.
26 Ibid., 5-7.
27 C Hadfield, op.cit., 71.
28 G Jars, Metallurgische Reisen zur Untersuchung und
Beobachtung de vornehmsten Eisen-, Stahl-, Blech-, und
Steinkohlenwerke in Deutschland, Schweden, Norwegen, England
und Schotland von Jahr 1757 bis 1769: Berlin, 1777-85; J
M Dutens, Mémoires sur les travaux publics de
l'Angleterre: Paris, 1819; H Fournel & I Dyèvre,
Mémoires sur les canaux souterrains et sur les
houillères de Worsley près Manchester:
Paris, 1842.
29 P K Roberts, Boat Levels Associated with Mining: I.
Coal Mining, Industrial Archaeology Review,
5.2, Spring 1981, 85-95.
30 C Hadfield, op.cit., 1986, 305-7; Hahn et al.,
op.cit., 24-5.
31 C Hadfield, op.cit., 1986, 136-37.
32 B Trout, The Biwako Canal, Waterways News,
77, February 1978, 4-5.
33 G J Thompson, Japan's Biwa Canal: All-Purpose Water
Utilization, American Canals, 83, November 1992, 4-7.
34 D Tew, op.cit., 1984, 62.
35 Ibid., 62-67.
36 Ibid., 72-74.
37 Ibid., 75-77.
38 Ibid., 77-78.
39 Ibid., 78-80.
40 Ibid., 78-79.
41 C Hadfield, op.cit., 1986, 351-53.
42 R Greenhill, The Peterborough lift lock, in D Newell
and R Greenhill, Survivals: Aspects of Industrial
Archaeology in Ontario, 209-26: Boston, 1989.
43 C Hadfield, op.cit., 1986, 135-36.
44 Correspondence from Ing. Jaroslav Kube_ (Czech
Republic).
45 C Hadfield, op.cit., 1986, 62.
46 N Crowe, English Heritage Book of Canals, 36:
London, 1994; C Hadfield, op.cit., 1976, 11.
47 W J Sivewright, Civil Engineering Heritage: Wales &
Western England, 195-96: London, 1986.
48 D Tew, op.cit., 77-78.
49 Ibid., 78-79.
50 As 42.
51 E Schinkel, Altes Schiffshebewerk Henrichenburg:
Dortmund, 1992.
52 Mackenzie Archive, Institution of Civil Engineers,
London.
53 H-J Uhlemann, Berlin und die Murkischen
Wasserstrassen: Hamburg, 1994.
54 N Smith, A History of Dams, 164-5: London, 1971.
55 J Needham, op.cit., 313-19. The idea for an
entirely new section of canal on the main north-south link of
the Grand Canal was conceived in AD 1275. This, the Hui
Thung Ho (Union Link Channel) was built southwards from
the existing Grand Canal to cross the northern course of the
Yellow River at right-angles. It was implemented in 1289 by
the magistrate of Shou-chang, Han Chung-Hui, and another
astronomer, Shih Pien-Yuan. The latter did the actual
survey. Chang Khung-Sun and a Mongol, Loqsi, were the
engineers in charge of the work, which was completed within
the year. It had 31 locks (mu chha) in a distance of
some 250 li (about 80 miles) and had the popular name
Chha Ho. It crossed a newly diminished branch of the Yellow
River at a point south of Tung-a in western Shantung and
reached as far as An-Shan near Tung-phing, where it met the
northern end of the summit level completed six years before.
On the way it incorporated the short canal, the Chhing Chi
Tu, which had been built by Hsun Hsien in AD 352. The
important summit section of the completed 1035 mile new line
of the Grand Canal was itself the work of a Mongol military
engineer, Oqruqui, in 1283 and the following years. It had
been built in accordance with plans drawn up by Kuo
Shou-Ching and the canal was conveyed through a cutting 30ft
deep. The canal was known as the Chi Chou Ho and at
its northern end connected with the Chhing Chi Tu of
AD 352 and at its southern end, at Chi-ning, with the Huan
Kung Kou, built in AD 369 for the campaigns of Marshal
Huan Wen. The summit level of the 1280s was 138ft above sea
level and always caused problems for the overall use of the
canal, so that the parallel sea-trade prospered. As a
consequence the central and most difficult parts of the Grand
Canal were remodelled to a high level of efficiency in 1411.
This was carried out by Sung Li, an engineer who had trained
at the Imperial University and been the Minister of Works, at
the proposal of the Assistant Administrator of Chi-ning, Phan
Cheng-Shu. He was advised by "an old countryman" (probably
an irrigation-worker) of Wen-shang, Pai Ying, who showed how
the waters of the Wen and Kuang Rivers could be used more
effectively. Pai Ying suggested that a new 1 mile long bund
or dam be constructed on the latter north of Ning-yang to
form a reservoir which would always keep the canal full, with
the aid of a forking lateral canal from the former, and these
major works were successfully completed in 200 days by a
force of 165,000 men. Sung Li also installed four small
reservoirs near the canal itself, known as "water boxes"
(shui kuei). These may have been the first side
pounds. They were repaired and enlarged in 1540 and 1616.
56 C Hadfield, op.cit., 1986, 23.
57 Personal communication, Michael Clarke.
58 C Hadfield, op.cit., 1976, 9.
59 Ibid., 10 & W J Sivewright, op.cit., 114-15.
60 T F Hahn et al., op.cit., 3.
61 B Fletcher, A History of Architecture on the
Comparative Method, 17th edition, ed R A Cordingley,
235-36; London, 1967.
62 E W Paget-Tomlinson, The Complete Book of Canal and
River Navigations, 29: Wolverhampton, 1978.
63 D H Shayt, Pennsylvania, in B Trinder (ed), The
Blackwell Encyclopedia of Industrial Archaeology, 561:
Oxford, 1992; C Hadfield, op.cit., 1986, 307.
64 Informationen zum Wasserstrassenkreuz Minden,
Wasser und Schiffahrtsamt Minden.
65 C Hadfield, op.cit., 1986, 34-35.
66 Ibid., 43.
67 C Hadfield & A W Skempton, William Jessop,
Engineer.
68 W J Sivewright, op.cit., 36-7.
69 Ibid., 179-80.
70 C Hadfield, op.cit., 1986, 307.
71 Ibid., 298.
72 D H Shayt, op.cit., 561.
73 J H Burns (ed), Recording Historic Structures,
8, 150, 225: Washington, 1989.
|